During severe storms when survival becomes a major concern,it may become necessary to relieve high anchor tensions on the windward side of the unit by().
A.deballasting the rig
B.ballasting the rig
C.paying out cable on the windward side
D.paying out cable on the leeward side
答案
参考答案:D