问题 单项选择题

Which of the following statements regarding capital budgeting is correct A firm’s optimal capital budget can be found by moving along its investment opportunity schedule until: ()

A. it exhausts its capital budget. 

B. the marginal revenue product is equal to marginal cost. 

C. the next project’s return no longer covers the marginal cost of capital.

答案

参考答案:C

解析:

The firm would not want to exhaust its capital budget on "bad" projects, (i. e. projects with IRR<cost of capital [NPV<0]). They should continue to invest as long as the project’s return is greater than the marginal cost of capital of the firm. When the project’s IRR=cost of capital, the NPV=0. This project will only make the firm larger; it will add nothing to the stock price. The investment opportunity schedule plots expected project returns from highest to lowest IRR.

单项选择题 A1型题
单项选择题