In 2000, Able Builders, Inc. was awarded a contract to build a bridge for the City of Metropolis. A reliable estimate of the total cost of the contract was $ 60000000. The contract price was $ 80000000. All invoices were paid in cash in the year the invoice was submitted. A schedule of revenues received and costs incurred during the contract was as follows (in $ millions):
A.
B.2001
C.2002
D.2003
E.2004
F.Amount Invoiced
G.l0
H.30
I.30
J.10
K.Costs Incurred
L.12
M.22
N.21
O.5
参考答案:B
解析:Under the installment sales method, revenue is recognized when the cash is received. Because Able Builders receives $ 30 million in cash (invoices were paid in cash in year they were submitted) $ 30 million in revenue is recognized. Note that the installment sales method would also result in the highest gross profit in 2003. Since costs are 75 percent of sales (60/80), costs of $ 22.5 million would be recognized resulting in a gross profit of $ 7.5 million. Under the cost recovery method, revenues are recognized only to the extent of costs incurred until all costs are collected, so revenues recognized through the end of 1999 would be ($12+$22=) $ 34 million. In 2003, not all COGS have been collected, so revenue of $21 million would be recognized to equal the costs incurred for that year. Gross profit would be $ 0. Under the completed contract method, no revenue is recognized in 2003 because all $ 80 million of revenue is recognized in 2004.