The calculation of the income recognized in the third year of a five-year construction contract accounted for using the percentage-of-completion method includes the ratio of:()

A. costs incurred in year 3 to total estimated costs.

B. total costs incurred to date to total billings to date.

C. total costs incurred to total estimated cost.

答案

参考答案:B

解析:

The percentage of completion method recognizes revenues in proportion to the proportion of expenses incurred.