在施工单位项目管理实施规划中,机械设备需求计划是( )的内容。
A.施工部署 B.施工方案 C.资源供应计划 D.施工进度计划
参考答案:C
All of the following occurred during the planning process group EXCEPT ______ .
A.develop project charter
B.create WBS
C.estimate costs
D.sequence activities