焦炭塔改油汽预热前需要做哪些工作?
答案
参考答案:
1.接到除焦班通知已除完焦,焦炭塔操作工应对塔底转油线进行吹扫;
2.装卸工装好头盖后,将新塔呼吸阀及放水阀关严并检查其它有关阀门是否关好。改蒸汽试压至规定值,恒压时间不得少于10分钟。检查头盖及短管是否泄漏;
3.试压完后泄压脱水,泄压后关严放空阀,脱水阀、冷焦阀。稍打开预热阀改少量油汽预热新塔,改通塔底至甩油罐的流程。
焦炭塔改油汽预热前需要做哪些工作?
参考答案:
1.接到除焦班通知已除完焦,焦炭塔操作工应对塔底转油线进行吹扫;
2.装卸工装好头盖后,将新塔呼吸阀及放水阀关严并检查其它有关阀门是否关好。改蒸汽试压至规定值,恒压时间不得少于10分钟。检查头盖及短管是否泄漏;
3.试压完后泄压脱水,泄压后关严放空阀,脱水阀、冷焦阀。稍打开预热阀改少量油汽预热新塔,改通塔底至甩油罐的流程。
King’s College Summer School King’s College Summer School is an annual(每年的)training program for high school students at all levels who want to improve their English.Courses are given by the teachers of King’s College and other colleges in New York.Trips to museums and culture centers are also organized.This year’s summer school will be from July 25 to August 15.More information is as follows:
|