问题
多项选择题
()因素能影响项目变化。
A.项目的生命期
B.项目经理的素质
C.项目计划
D.项目的组织
E.外部因素
答案
参考答案:A, B, D, E
()因素能影响项目变化。
A.项目的生命期
B.项目经理的素质
C.项目计划
D.项目的组织
E.外部因素
参考答案:A, B, D, E
听短文,根据所听内容选出短文中划线部分词的同义词或同义短语。 | |||
Some people think we buy too many gifts before Christmas. So they have started a special day 1 Buy Nothing Day. They 2 anyone to go shopping on that day. Buy Nothing Day is after Thanksgiving and it is often the 3 of Christmas shopping. At that time, we see ads in newspapers and on TV telling us to "BUY! BUY! BUY!". The idea for Buy Nothing Day started in Canada. Now people all over the world celebrate Buy Nothing Day. In California, parents and children get together to read stories, sing songs and draw pictures. The children talk about why they don't get 4 toys. In New Mexico, high school students made posters to give people information about Buy Nothing Day. Most people 5 the new idea. They decided not to buy anything on that day every year. | |||
|