Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. ______ is following the process-Estimate Activity Durations.

A.Estimate Activity Resources

B.Define Activities

C.Develop Schedule

D.Sequence Activities

答案

参考答案:C

解析:[参考译文] 项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是进度计划编制(Develop Schedule)。