Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. ______ is following the process-Estimate Activity Durations.
A.Estimate Activity Resources
B.Define Activities
C.Develop Schedule
D.Sequence Activities
答案
参考答案:C
解析:[参考译文] 项目进度管理包含多个项目实效管理过程,这些过程相互影响,其中紧接活动历时估算的过程是进度计划编制(Develop Schedule)。