问题 单项选择题

PDM includes four types of dependencies or precedence relationships.______, the initiation of the successor activity, depends upon the initiation of the predecessor activity.

A.Start-to-Start

B.Finish-to-Finish

C.Start-to-Finish

D.Finish-to-Start

答案

参考答案:A

解析:[参考译文] 前导图法包括四种活动依赖或前导关系。开始——开始(S-S),后续活动的开始依赖于前置活动的启动。