问题 单项选择题

The ______ Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

A.Planning

B.Executing

C.Monitoring and Controlling

D.Close-out

答案

参考答案:B

解析:[参考译文] 执行(Executing)过程组由为达成项目要求而在项目管理计划中定义的工作的过程组成。

单项选择题
单项选择题