已知某工程的计划工作预算费用为5000万元,已完工作预算费用为6000万元,已完工作实际费用为5800万元,则此工程的进度绩效指数为()。
A.0.7
B.0.9
C.1.02
D.1.2
答案
参考答案:D
已知某工程的计划工作预算费用为5000万元,已完工作预算费用为6000万元,已完工作实际费用为5800万元,则此工程的进度绩效指数为()。
A.0.7
B.0.9
C.1.02
D.1.2
参考答案:D
完型填空 | ||||
Many children have birthday cakes on their birthdays. In some ___1___, like England and Scotland, there is another custom, too. People beat or hit the___2___on his/her birthday. This may hurt___3___, but they say it is very lucky for the child. The child must ___4___cry. The custom says, if you ___5___, you will cry all year. They say the birthday spanks (一巴掌) is to make the bad spirits(邪气) ___6___. The harder you spank the better. In Belgium, another country in Europe, the custom is a little __7___. There a parent goes into the child's room ___8___in the morning with a needle. As soon as the child ___9___ up, the parent pricks(刺) the child with the needle. This is for good __10____. | ||||
|