下列有关工程项目目标的表述中不正确的是( )。
A.工程项目管理实际上就是一种目标管理
B.工程项目目标就是实施一个工程项目所要达到的预期结果
C.工程项目目标必须明确、可行、具体和可以度量
D.工程项目目标不一定在投资方与业主、承包商之间达成一致
答案
参考答案:D
解析:工程项目目标必须明确、可行、具体和可以度量,并须在投资方与业主、承包商之间达成一致。
下列有关工程项目目标的表述中不正确的是( )。
A.工程项目管理实际上就是一种目标管理
B.工程项目目标就是实施一个工程项目所要达到的预期结果
C.工程项目目标必须明确、可行、具体和可以度量
D.工程项目目标不一定在投资方与业主、承包商之间达成一致
参考答案:D
解析:工程项目目标必须明确、可行、具体和可以度量,并须在投资方与业主、承包商之间达成一致。
I was cleaning out an old box when an old card caught my eye: Queen City Casket Company. “What is it? ”I wondered. I it over. There, in faded ink, was a hand-scrawled . Immediately my mind back many years ago. ![]() I was nine years old, walking down the cold, wet streets of Springfield, with a bag of on my shoulder. On my that day, I came to that company finally, whose owner, Mr. Rader, had always taken me there to his workers whether they wanted any magazines. off the rain like a wet dog, I entered Mr. Rader’s office. After a quick glance he me over to the fireplace. Noticing the in the top of my , he said, “Come with me! ”pulling me into his truck. We before a shoe store. Inside, a salesman me with the finest pair of Oxfords I had seen. I felt about 10 feet tall when I got up them. “We’d like a pair of new socks too, ”Mr. Rader said. Back in his office, Mr. Rader took out a , wrote something on it, and handed it to me. With tearful eyes, I read, “ to others as you would have them do to you. ”He said affectionately(亲切地), “Jimmy, I want you to I love you. ” I said goodbye, and for the first time I a flicker of hope that somehow things would be all right. With people like Mr. Rader in the world, there was hope, and love, and that would always make a .
|