An appropriate sequence for risk management activities is______.
A.identify risks,perform qualitative risk analysis,perform quantitative risk analysis,plan risk responses
B.identify risks,risk assessment。and risk planning
C.identify risks,risk mitigation,and risk management
D.identify risks,risk elimination,and risk mitigation
答案
参考答案:A