A response to a risk that was not defined in advance of its occurrence is called a______.
A.risk mitigation response
B.workaround response
C.corrective action response
D.contingency response
答案
参考答案:B
解析: 对一项在发生之前未界定的风险事件作出响应称为______。 A) 风险缓解反应 B) 权变措施 C) 纠正行动响应 D) 应急反应 权变措施是针对负面风险正在发生时采取的事先未计划的措施。