You are managing the construction of luxury condominiums in one of the last available plots of city land. On this project, the owner is focused on timely performance and has provided contract incentives that will reward you and your company if the job is complete early. However, the International Brotherhood of Commode Installs is ready to strike for higher wages, and an environmental group is concerned about adverse impacts on the full-breasted warbler resulting from the placement of satellite dishes on the balconies. On this project, you need to ().
A.find appropriate resolutions to resolve differences between or among stakeholders
B.put the owner's requirements at the top of the list as you resolve stakeholder differences
C.carefully manage all communication and make status information available only on a need-to-know basis
D.build the condominiums according to the specifications and not worry about any other stakeholder