问题 单项选择题

The critical path ______.

A) is the earliest series of events and activities which have the highest technical risk in the project
B) is the series of events and activities which have the highest cost in the project
C) is the longest chain of events and activities from today's date to the end of the project, if the plan represented by the current network plan is executed
D) is an interesting concept, but is has little significance to the project functional managers assigned to the project

答案

参考答案:C

解析:关键路径______。
A) 是最早一系列在项目中具有最高技术风险的事件和活动
B) 是一系列在项目中具有最高成本的事件和活动
C) 如果按现有网络计划执行的话,是项目生命期中最长的一系列事件和活动
D) 是一个有趣的概念,对于项目的职能经理来说影响不大