If Task B has 15 days of free float and 25 days of total float, and the early start date of Task B is delayed 30 days, how is the project affected

A) The next dependent task's start date will be delayed 15 days.
B) The duration of the task will be shortened 15 days.
C) The completion date of the project will be pushed out 5 days.
D) Both A and C.

答案

参考答案:D

解析:如果任务B有15天的自由时差和25天的总时差,并且最早开始时间延迟了30天,对项目有什么影响
A) 下一个相关的任务会延迟15天。
B) 任务会缩短15天完成。
C) 项目会推迟5天完成。
D) A和C。