Time planning ______.
A) involves determining how the various tasks required to completed the project, and the activities within the tasks, will be accomplished in terms of sequence and dependency
B) refers to setting up the vacation schedule for each member of the project team
C) is the sole responsibility of the project scheduling department
D) is having a well staked scheduling department
答案
参考答案:A
解析:时间计划______。
A) 涉及如何将不同的任务按顺序和相互关系结合在一起来完成整个项目
B) 指的是为项目成员制定休假计划
C) 是项目进度规划部门的唯一责任
D) 是拥有一个良好的进度规划团队