在EPC模式中,采购主要是指( )。
A.工程采购
B.货物采购
C.服务采购
D.招标采购
答案
参考答案:B
解析:按世界银行的定义,采购包括工程采购(通常主要是指施工招标)、服务采购和货物采购。采购主要是指货物采购即材料和工程设备的采购。EPC模式在名称上突出了Procurement,表明在这种模式中,材料和工程设备的采购完全由EPC承包单位负责。
在EPC模式中,采购主要是指( )。
A.工程采购
B.货物采购
C.服务采购
D.招标采购
参考答案:B
解析:按世界银行的定义,采购包括工程采购(通常主要是指施工招标)、服务采购和货物采购。采购主要是指货物采购即材料和工程设备的采购。EPC模式在名称上突出了Procurement,表明在这种模式中,材料和工程设备的采购完全由EPC承包单位负责。
完形填空。 | ||||
For me, Christmas always began in the middle of the cold, windy month of November. My sister Alice and I sat down in front of the fire and wrote a 1 to Father Christmas, telling him about all the presents we 2 . We carefully posted the letter to "Father Christmas, the North pole"… Christmas Eve came, The whole family helped to 3 the house, put up the Christmas tree and blow up the balloons. Then, in the afternoon, when Aunt Kate and my two cousins arrived, 4 was ready. Before we went to bed, we left some wine and meat for Father Christmas and then put our 5 at the end of our beds. We tried to keep 6 as long as possible to see Father Christmas, but the next thing we knew it was 7 Christmas morning! We couldn't wait to 8 the stocking. It was now full of all kinds of small present and sweets. Christmas morning was bright and sunny. After going to church, my cousin David and I went out into the garden to 9 our new present. Lunch was always late, but what a lunch! Delicious turkey with all the vegetables followed by fruits and ice creams. 10 lunch, Father, Mother and Aunt rested on the sofas in front of the Queen's speech on TV. We took out the toys, put on the funny paper hats, laughed at the jokes and played 11 . Then came the afternoon tea and a large 12 cake covered with snowmen. It didn't seem possible, 13 we still went on eating. By bedtime all of the children were very 14 . As soon as Mom 15 the light, we all fell into a deep sleep. | ||||
|