You are the project manager of a large software development project. There is a conflict between two module leads on where the changes have to be made. You intervene and tell them the importance of getting the project on time and ask them to find a solution which is acceptable to both of them. Which conflict resolution technique are you using here ?()
A.Confronting
B.Compromising
C.Smoothing
D.Forcing
参考答案:C
解析:
你是个大型软件开发项目的项目经理。两个模块组长之间在什么地方做变更上出现了冲突。你介人告诉他们按时完成项目的重要性,要求他们找出双方都能接受的方案。你在这里使用的是哪种冲突解决方案
A) 面对。 B) 妥协。 C) 调和。 D) 强制。
你要求他们找出双方都能接受的方案,即求同存异,属于调和。