问题 单项选择题

If a CV was positive and the SV was positive, what does this indicate ?()

A.The project is over budget, but on schedules.

B.The project is under budget, but behind schedules.

C.The project is under budget, and ahead of schedules.

D.The project is on budget and on schedules.

答案

参考答案:C

解析:

如果费用偏差是正的而进度偏差也是正的,这意味着什么

A) 项目超出预算,但按计划进行。

B) 项目在预算内,但落后计划。

C) 项目在预算内并提前于计划。

D) 项目在预算内并按计划进行。