Being the project manager in a software project which is currently initiated, you want to assess high level risks. What should you do ?()
A.Develop a preliminary scope statement and document initially identified risks in this document.
B.Identify and analyze risk events using qualitative and quantitative techniques.
C.Develop contingency plans and fallback plans in case the original plan proves Wrong.
D.Discuss the risks documented in your risk register with the project key stakeholders.
参考答案:A
解析:
你是个项目经理,刚刚启动一个软件项目,你想评估最高层次的风险,你应该做什么
A) 编写初步范围说明书,记录下来最初识别的风险。
B) 使用定性和定量技术识别和分析风险事件。
C) 编写应急计划和后备计划以防原来的计划出现错误。
D) 和项目重要干系人对你风险登记册中的风险进行讨论。
选项B和D都是在风险被识别之后,属于规划过程组的内容;选项C是应对风险规划的内容。因为题干表明项目刚启动,只有选项A符合。