During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline schedule ().
A.now becomes the new schedule, including the changes, and the original baseline is disregarded
B.is still the original baseline but annotated to reflect that a change has taken place
C.is amended to reflect the scope change, but the original baseline is still maintained for post-project review
D.is meaningless since every schedule update changes the baseline
参考答案:C
解析:
在项目执行过程中,用户授权变更范围并调整了资金,由此带来了项目进度的大的变更。则项目进度基准______。
A) 变为新的进度表,包括了变更,原进度基准不再适用
B) 仍然是原进度基准,但要给出注释以反映已经发生的变更
C) 需要调整以反映范围变更,但原进度基准仍应维护以备项目后审查
D) 没有任何意义,因为每一次进度的更新都会改变进度基准
通常范围变化后,进度都需要进行调整。“一般是在批准项目范围或费用估算方面的变更请求……”。