问题 单项选择题

You are a project manager to upgrade the computer safety of your organization. Your project team is made up of four contractors and two full time employees. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: ().

A.Forming, storming, norming, and performing.

B.Storming, norming, forming, and performing.

C.Norming, storming, forming, and performing.

D.Forming, norming, storming, and performing.

答案

参考答案:A

解析:

你是个项目经理,正在更新你们组织的计算机安全系统。你的项目团队包括4个承包商和2个全职雇员。这是他们第一次一起工作,你知道这个团队将按照下列哪个顺序来发展:

A) 形成、震荡、规范、成熟。 B) 震荡、规范、形成、成熟。

C) 规范、震荡、形成、成熟。 D) 形成、规范、震荡、成熟。

Bruce Tuckman模型。

多项选择题
单项选择题 A1/A2型题