问题 单项选择题

A project manager does not have much time to spend planning before the mandatory start date arrives. He therefore wants to move through planning as effectively as possible. Which of the following would you recommend ?()

A.Make sure you have a completed preliminary project scope statement and then start the WBS.

B.Create an activity list before creating a network diagram.

C.Document all the known risks before you document the high-level assumptions.

D.Finalize the quality management plan before you determine quality metrics.

答案

参考答案:B

解析:

项目经理在强制开始日期到来之前没有太多时间可以用于规划,他希望尽可能使规划过程变得有效率。你将推荐下列哪项

A) 确保你完成初步范围说明书并开始创建WBS。

B) 在创建网络图之前创建活动列表。

C) 在你记录下高层次的假设之前记录下所有已知的风险。

D) 在你确定质量指标之前确定项目质量管理计划。