You have recently appointed a project manager to handle a critical project in your organization. You want to provide the project manager with authority to apply organizational resources to project activities. Which document should you use ?()
A.Resource authorization document
B.Work breakdown structure
C.Project charter
D.Project scope statement
参考答案:C
解析:
你最近指定了某个项目经理负责你组织的关键项目,你想给项目经理权限去应 用组织资源到项目活动上。你应该使用哪个文档
A) 资源授权文档。 B) 工作分解结构。
C) 项目章程。 D) 项目范围说明书。