问题 单项选择题

The software development project is not going well. There are over 30 stakeholders, and no one can agree on the project objectives. One stakeholder believes the project can achieve a 30 percent improvement while another believes a 50 percent improvement is possible. The project manager thinks a 10 percent improvement is more realistic. What is the BEST course of action ?()

A.Move forward with the project and look for more information later to settle the issue.

B.Average the numbers and use that as an objective.

C.Perform a feasibility analysis.

D.Ask the sponsor to make the final decision.

答案

参考答案:C

解析:

某个软件开发项目进展得并不好。该项目有30多个项目干系人,大家对项目目标没有达成一致的看法。一个项目干系人认为项目可以达到30%的改进效果,而另外一个认为达到50%是可能的。项目经理却认为10%的改进效果相对来说更加现实。面对这种情况,最应该采取的行动是

A) 继续往前推进这个项目,今后再收集更多的信息以解决这个问题。

B) 算出这些数字的平均值,并以此为一个目标。

C) 进行可行性分析。

D) 让项目出资人做最后的决定。

题干表明此项目处于启动阶段,可行性研究将帮助明确项目的目标。