In your project, you want to monitor and control project processes associated with initiating, planning, executing and closing. This will help you take corrective or preventive action to control project performance. In this context, what should you do first ?()
A.Review all project forecasts
B.Detail all the activities of project team members involved in executing administrative closure for the project
C.Review the project management plan and work performance information for your project
D.Manage project risks
参考答案:C
解析:
在你的项目中,你想监控项目启动、规划、执行、收尾等过程,这将帮助你采取纠正措施或预防措施来控制项目绩效。在这种情况下,你首先应该做什么
A) 回顾所有项目预测。
B) 在执行管理收尾时详细所有项目团队的活动。
C) 回顾项目管理计划和项目的工作绩效信息。
D) 管理项目风险。
这道题等于问哪个是监控项目的输入。