Being assigned as the project manager to a project you perform earned value Analysis and find the following results: EV=250000; PV=200000; AC=275000; BAC=500000. What is right ?()
A.EAC=400000
B.EAC=550000
C.BTC=400000
D.ETC=75000
答案
参考答案:B
解析:
在项目上你做了实现值分析,发现下列结果:EV=250000;PV=200000;AC=275000;BAC=500000。下列哪项是正确的
A) EAC=400000。 B) EAC=550000。
C) BTC=400000。D) ETC=75000。
EAC=BAC/CPI=500000×1.1=5500O0。默认情况下按照典型偏差计算即可。