问题
单项选择题
A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ______.
A.change the scope baseline
B.call a meeting of the configuration control board
C.assign change tasks to project members
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
答案
参考答案:D
解析:[参考译文] 项目经理认为调整项目范围可以给客户提供增值的服务。项目经理应该暂缓修改,按照原先的基线执行,直至在改进项目会上得到客户的认可和增加相应资金。