单项选择题
The (72) technique involves using project characteristics in a mathematical model to predict total project costs. Models can be simple or complex.
A.Cost Aggregation
B.Reserve Analysis
C.Parametric Estimating
D.Funding Limit Reconciliation
答案
参考答案:C