问题 单项选择题

The project manger should seek speedy resolutions o conflict between the project and functional departments primarily because ______.

A) conflict impedes the decision making necessary to stay within schedule and budget constraints
B) conflict represents a challenge to authority
C) conflict indicates that the project management concept is not well understood
D) the resolution o conflict is a problem to be resolved by the manager of project managers

答案

参考答案:A

解析:使用排除法,B、C、D明显不对,所以选A。
项目经理应该在项目和职能部门冲突时寻求快速的解决方法,这是由于______。
A) 决策制定对于进度和预算限制十分必要,而冲突会妨碍决策的制定
B) 冲突代表对权威的挑战
C) 冲突说明项目管理概念没有得到良好理解
D) 冲突是由项目经理的经理解决的问题

填空题
选择题