Timely decisions directly affect the ability of the project team to meet commitments to cost and schedule constraints. Therefore ______.
A) the project team must be able to make decisions or obtain fast decisions from upper management
B) functional department should make their decisions as quickly as possible
C) upper management should communicate decisions to the project team at least weekly
D) since consensus decision making is time consuming, provisions have been made for budget and schedule revisions
参考答案:A
解析:使用排除法。
及时的决策直接影响到项目团队在费用和进度均有限制的条件下执行项目的能力,因此______。
A) 项目团队必须能够做出决策或从上层管理获得快速决策
B) 职能部门应该尽快地做出决策
C) 上级管理层应该至少每周和项目团队交流决策
D) 由于做出一致决定十分耗时,应该为预算和进度修改做出预留