问题 单项选择题

The Time Management function as it relates to personnel ______.

A) refers primarily to the manner in which the project manager and the various functional contributions to the project manage their time on a daily basis
B) should not be emphasized because it develops a "clock-watching" mentality in the project team
C) consists of four overlapping processes, planning, estimating, scheduling, and controlling
D) consists of two overlapping processes, planning and controlling

答案

参考答案:C

解析:时间管理功能和人员有关联______。
A) 主要是指项目经理以及参与项目的各职能部门管理他们日常工作时间安排的基准
B) 由于这会引起项目团队“看钟”的心理特性,所以不应该强调
C) 包括四个重叠的过程、计划、估计,进度规划和控制
D) 包括两个重叠的过程,计划和控制