问题 单项选择题

The close project or phase process is essential to overall project planning. What is considered one of the most important steps in closing project or phase

A) Insuring that plans are produced to implement the project by phases.
B) Issuing work orders so that financial data can be collected.
C) Transition the lease of equipment to the owner.
D) Satisfying the contractual obligations.

答案

参考答案:D

解析:合同条款与条件也可能对合同收尾做了具体规定,若有规定,则必须执行。结束项目或阶段必须满足合同要求。
结束项目或阶段过程对整个项目计划十分重要。在结束项目或阶段中最重要的一步是下列哪个
A) 说明计划是分阶段来实施项目的。
B) 提供工作清单以便收集财务数据。
C) 转变设备的租约给业主。
D) 满足合同要求。