Your project has a number of different work results. You are collecting information about these work results such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding. You will use this information in which of the following processes
A) Direct and manage project execution.
B) Perform integrated change control.
C) Reprot performance.
D) Verify scope.
参考答案:C
解析:报告绩效给出完成可交付成果状态的信息。
你的项目有一些工作结果。你正在收集关于这些工作结果的信息,包括有哪些方面消耗了项目的成本,完成了哪些可交付产品以及哪些还没有完成。你将在下列哪项流程中使用这些信息
A) 指导与管理项目执行。
B) 实施整体变更控制。
C) 报告绩效。
D) 核实范围。