问题 单项选择题

Your company's project review committee (PRC) meets quarterly to review any project with a budget exceeding $2 million. You recently were promoted to senior project manager and were assigned one of these largest projects, the development of a next-generation, computer-aided manufacturing process. The PRC asked you to present the project's objectives, work content, and deliverables at its next meeting. Accordingly, you need to prepare which one of the following documents

A) project charter.
B) product description.
C) scope statement.
D) WBS.

答案

参考答案:C

解析:范围说明指明项目的目标、工作内容和成果。
你的公司的项目审查委员会每个季度召开会议审查所有预算超过二百万美元的项目。你最近被提升为高级项目经理,并承担了最大的项目之一,即开发下一代计算机辅助生产流程。审查委员会要求你在下次会议上说明项目的目标、工作内容和成果。为此你需要准备以下哪个文件
A) 项目章程。
B) 产品描述。
C) 范围说明。
D) 工作分解结构。