Precedence Diagramming Method (PDM) is a method used in activity sequencing.There are four types of dependencies or precedence relationships in PDM.The initiation of thesuccessor activity depends upon the completion of the predecessor activity is called ______.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish