In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT ______ .
A.activities that are not required as part of project scope
B.activities that are to be performed as part of the project
C.activity identifier and scope of work description for each schedule activity
D.all the above are included in the activity list