An analyst does research about revenue recognition andgathers the following information about a construction contract with outcome that can be reliably measured:
·Estimated total revenues to be collected is $250000
·Estimated total costs to be incurred is $175000
·Cash collected during year 1 is $100000
·Costs incurred during year l is $ 80 000()
Assuming the project will be completed after 4 years, the revenue from the contract recognized for year 1 is closest toA. $0
B. $142857
C. $114285