You recently took over a large project from another project manager who had to leave for a personal emergency.You want to understand what kind of information should he provided to different stakeholders,and what methods should he used to provide this information.You will find this information in the______.

A.communications management plan

B.performance reports

C.project records

D.communication plan

答案

参考答案:A

解析: 最近你从另一项目经理那里接手了一个大型项目,他因为个人的突发事件离开了。你想知道项目关系人分别获得何种信息,通过什么方法来获得这些信息。你会在______中找到这些信息。 A) 沟通管理计划 B) 绩效报告 C) 项目记录 D) 沟通计划 沟通管理计划能提供沟通信息,包括格式、内容和细节标准以及传达信息所用的技术方法。