问题
单项选择题
Your project has a number of different work results.You are collecting information about these work results,such as what costs have been incurred or committed and which deliverables have been completed and which remain outstanding.You will use this information in which of the following processes
A.Project plan executio
B.Integrated change contro
C.Report performanc
D.Verify scop
答案
参考答案:C