问题 阅读理解
阅读理解。
      Skin-diving (潜水) is a new sport today. This sport takes you to a new wonderful world. It is like a
visit to the moon! When you are under the water, it is easy for you to climb big rocks (岩石), because you
are no longer (不再) heavy.
      Here, under the water, everything is blue and green. During the day, there is enough light. When fish
swim nearby, you can catch them with your hands. When you have a tank (罐) of air on your back, you
can stay in deep (深) water for a long time. But you must be careful when you dive in deep water. To catch
fish is one of the most interesting parts of this sport.
      Besides (除此以外), there are more uses for skin-diving. You can clean ships without taking them out
of the water. You can get many things from the deep water. Now you see the skin-diving is useful and
interesting.
1. Skin-diving is going to take you to _____.
[ ]
A. the deep water
B. be in danger
C. mountains
2. You can climb big rocks easily under the water because _____.
[ ]
A. you are stronger
B. the fish nearby help you
C. you are lighter than on land
3. Under the water, a skin-diver _____ in the daytime.
[ ]
A. can see everything clearly
B. can't see anything clearly
C. can see nothing
4. With a tank of air on your back, you can _____.
[ ]
A. catch fish very easily
B. stay under the water for a long time
C. have more fun
5. From the passage we can know that skin-diving is _____.
[ ]
A. harmful
B. not useful
C. useful and interesting
答案

1-5: ACABC

问答题

某工程采用公开招标方式,招标人3月1日在指定媒体上发布了招标公告,3月6日至3月12日发售了招标文件,共有A、B、C、D 4家投标人购买了招标文件。在招标文件规定的投标截止日(4月5日)前,4家投标人都递交了投标文件。开标时投标人D因其投标文件的签署人没有法定代表人的授权委托书而被招标管理机构宣布为无效投标。

该工程评标委员会于4月15日经评标确定投标人A为中标人,并于4月26日向中标人和其他投标人分别发出中标通知书和中标结果通知,同时通知了招标人。

发包人与承包人A于5月10日签订了工程承包合同,合同约定的不含税合同价为6948万元,工期为300天;合同价中的间接费以直接费为计算基数,间接费费率为12%,利润率为5%。

在施工过程中,该工程的关键线路上发生了由以下几种原因引起的工期延误:

(1)由于发包人原因,设计变更后新增一项工程于7月28日至8月7日施工(新增工程款为160万元);另一分项工程的图纸延误导致承包人于8月27日至9月12日停工。

(2)由于承包人原因,原计划于8月5日晨到场的施工机械直到8月26日晨才到场。

(3)由于天气原因,连续多日高温造成供电紧张,该工程所在地区于8月3日至8月5日停电,另外,该地区于8月24日晨至8月28日晚下了特大暴雨。

在发生上述工期延误事件后,承包人A按合同规定的程序向发包人提出了索赔要求。经双方协商一致,除特大暴雨造成的工期延误之外,对其他应予补偿的工期延误事件,既补偿直接费义补偿间接费,间接费补偿按合同工期每天平均分摊的间接费计算。

问题

图纸延误应予补偿间接费为多少

单项选择题