问题
单项选择题
Your project is behind schedule due to conflict between team members.Having resolved the conflict,to get the project back on schedule,you should consider()
A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chair resources
答案
参考答案:A
解析:
由于团队成员之间的冲突,造成了项目进度落后于计划,为了解决冲突以使得项目如期完成,你应该考虑:
A.重新安排时间表
B.执行资源调配
C.进行反向资源分配调度
D.利用关键的主要资源