Changes may be requested by any stakeholder involved with the project,but changes can be authorized only by()
A.executive IT manager
B.project manger
C.change control board
D.project sponsor
答案
参考答案:C
解析:
参考译文
项目变更可以由IT经理(executive IT manager)、项目管理者(project manager)、项目发起人(project sponsor)等任意项目干系人发起,但只能由变更控制委员会(change control board)授权通过,所以选C。