You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent¥260,000 0fyour budget to complete work that you originally expected to cost ¥280,000.According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be best described as ()

A.ahead of schedule

B.behind schedule

C.on schedule

D.having not enough information provided

答案

参考答案:B

解析:

参考译文:你是一个项目经理。你目前负责的项目预算是50万元,工期是6周。到目前为止,你已经花费了26万元工程款,完成了预算中28万元的工作量。根据你之前制定的进度计划,到目前为止,你应该花费30万元工程款。根据这些描述,你的工程目前____。