A work breakdown structure (WBS) is a tool used to define and group a project's discrete work elements in a way that helps organize and define the total work scope of the project. A WBS is most useful for()
A.identify ingindividual tasks for a project
B.scheduling the startoftasks
C.scheduling the end oftasks
D.determining potential delays
答案
参考答案:A
解析:参考译文:工作分解结构(WBS)是一个用于定义和组织项目离散工作要素的工具,帮助组织和定义项目的整个工作范围。工作分解结构最重要的作用是"______"。