Software architecture reconstruction is an interpretive, interactive, and iterative process including many activities. (1) involves analyzing a system's existing design and implementation artifacts to construct a model of it. The result is used in the following activities to construct a view of the system. The database construction activity converts the (2) contained in the view into a standard format for storage in a database. The (3) activity involves defining and manipulating the information stored in database to reconcile, augment, and establish connections between the elements. Reconstruction consists of two primary activities: (4) and (5). The former provides a mechanism for the user to manipulate architectural elements, and the latter provides facilities for architecture reconstruction.

空白(4)处应选择()

A.architecture analysis and design

B.domain analysis and static modeling

C.visualization and interaction

D.user requirements modeling

答案

参考答案:C

解析:

软件架构重构是个解释性、交互式和反复迭代的过程,包括了多项活动。信息提取通过分析系统现有设计和实现工件来构造它的模型。其结果用于在后续活动中构造系统的视图。数据库构建活动把模型中包含的元素和关系转换为数据库中的标准存储格式。视图融合活动包括定义和操作数据库中存储的信息,理顺、加强并建立起元素之间的连接。重构由两个主要活动组成:可视化和交互记及模式定义和识别。前者提供了一种让用户操作架构元素的机制,后者则提供了用于架构重构的设施。

单项选择题
问答题 案例分析题

【背景资料】

某新建办公大楼的招标文件写明:承包范围是土建工程、水电及设备安装工程、装饰装修工程;采用固定总价方式投标,风险范围内价格不作调整,但中央空调设备暂按120万元报价;质量标准为合格,并要求创省优质工程奖,但未写明奖罚标;合同采用《建设工程施工合同(示范文本)》GF一2013—0201。

某施工单位以3260万元中标后,与发包方按招标文件和中标人的投标文件签订了合同。合同中还写明:发包方在应付款中扣留合同额5%,即163万元作为质量履约保证金,若工程达不到国家质量验收标准,该质量履约保证金不再返还;逾期竣工违约金每天1万元;暂估价设备经发承包双方认质认价后,由承包人采购。

合同履行过程中发生了如下事件:

事件1:主体结构施工过程中发生了多次设计变更,承包人在编制的竣工结算书中提出设计变更实际增加费用共计70万元,但发包方不同意该设计变更增加费。

事件2:中央空调设备经比选后,承包方按照发包方确认的价格与设备供应商签订了80万元采购合同。在竣工结算时,承包方按投标报价120万元编制结算书,而发包方只同意按实际采购价80万元进行结算。双方为此发生争议。

事件3:办公楼工程经四方竣工验收质量为合格,但未获得省优质工程奖。发包方要没收163万元质量保证金,承包人表示反对。

事件4:办公楼工程实际竣工日期比合同工期拖延了10d,发包人要求承包人承担违约金10万元。承包人认为工期拖延是设计变更造成的,工期应顺延,拒绝支付违约金。

中央空调设备在结算时应以投标价120万元,还是以实际采购价80万元为准?说明理由。