The critical chain ______ .
A.focuses on managing the resources applied to buffer activities
B.alters the required dependencies in the project schedule to optimize resource constraints
C.adds duration buffers that are work schedule activities to maintain focus on the total float of network paths
D.adds duration buffers that are non-work schedule activities to maintain focus on the planned activity durations