Clare, Dan and Eve formed a partnership 10 years ago, although Clare was a sleeping partner and never had anything to do with running the business. Last year Dan retired from the partnership. Eve has subsequently entered into two large contracts. The first one was with a longstanding customer Greg, who had dealt with the partnership for some five years. The second contract was with a new customer Hugh. Both believed that Dan was still a partner in the business. Both contracts have gone badly wrong leaving the partnership owing €50,000 to both Greg and Hugh. Unfortunately the business assets will only cover the first €50,000 of the debt.Required:Explain the potential liabilities of Clare, Dan, and Eve for the partnership debts. (10 marks)

答案

参考答案:

单项选择题
问答题

(一)某市中心区新建一座商业中心,建筑面积26000m2,地322层,地上16层,1~3层有裙房,结构形式为钢筋混凝土框架结构,柱网尺寸为8.4m×7.2m,其中二层南侧有通长悬挑露台,悬挑长度为3m。施工现场内有一条10kV高压线从场区东侧穿过,由于该10kV高压线承担周边小区供电任务,在商业中心工程施工期间不能改线迁移。 某施工总承包单位承接了该商业中心工程的施工总承包任务。

该施工总承包单位进场后,立即着手进行施工现场平面布置:

①在临市区主干道的南侧采用1.6m高的砖砌围墙作围挡。

②为节约成本,施工总承包单位决定直接利用原土便道作为施工现场主要道路。

③为满足模板加工的需要,搭设了一间50m2的木工加工间,并配置了一只灭火器。

④受场地限制在工地北侧布置塔吊一台,高压线处于塔吊覆盖范围以内。

主体结构施工阶段,为赶在雨季来临之前完成基槽回填土任务,施工总承包单位在露台同条件混凝土试块抗压强度达到设计强度的80%时,拆除了露台下模板支撑。主体结构施工完毕后,发现二层露台根部出现通长裂缝,经设计单位和相关检测鉴定单位认定,该裂缝严重影响到露台的结构安全,必须进行处理,该事故造成直接经济损失877元。

问题:

工程质量事故按造成损失严重程度划分为哪几类?本工程露台结构质量事故属于哪一类?说明理由。